Timeline
The project runs for 36 months, starting in October 2025. Milestones are shown by project month.
Month 13 of 36
| # | Milestone | Months | Weight |
|---|---|---|---|
| 1 | Project Setup & Research Framework | 1–9 | 15% |
| 2 | Data Collection, Analysis & Preprocessing | 3–10 | 10% |
| 3 | PPA Review & AI-Powered Support ImplementationPPA review later removed from scopeIn progress | 4–15 | 15% |
| 4 | Training, Workshop & SeminarIn progress | 4–36 | 15% |
| 5 | Web-based Monitoring Platform & Device DevelopmentIn progress | 7–27 | 15% |
| 6 | AI Integration in Cost Modeling, Decision Support & MonitoringIn progress | 10–30 | 10% |
| 7 | System Integration, Testing & Validation | 16–33 | 10% |
| 8 | Final Report, Publication & Dissemination | 22–36 | 10% |